Silvermine River Dams – Wilton, CT – Private Scope: Remove and Replace (2) dams, Install Fishway, Stop Log Structure, Streambank Protection, Cofferdam and Water Control
New Canaan Field Club – New Canaan, CT – Private Scope: Remove and Replace (2) dams, Stop Log Structures, Streambank Protection
Indian Lake Dam – Milford, CT – Lake Association Scope: Remove Spalled Concrete, Install Concrete Cap on Spillway
Samp Mortar Dam -Fairfield, CT – Lake Association 2001 ,2002,2003,2009,2010 Scope: Install H Beams around Inlet Structure encase in concrete, remove valves, install sluice gates, crack repair with chemical grout, joint repair, remove delaminated concrete on wingwalls and replace.
Beaver Lake Dam – Bedford, NY – Lake Association Scope Replace 200 ft spillway, Install Downstream Rip Rap, Streambank Protection
Northfield Pond Dam – Northfield, CT – Connecticut Dept of Environmental Protection Scope: Poured Reinforced Concrete Walls, Cantilevered Spillway, New Inlet Structure, Sluice Gate, Stop Log Stucture, Cofferdam, Water Control
Middle River Dams #1, #2 – S. Windsor, CT – State of Ct DEP Scope: Seal joints, Cover Rip Rap, Reconstruct Dike, Inlet Riser Modifications, Slope Protection
Avery Brook Dams #4, #5 – Stafford, CT – State of Ct DEP Scope: Reconstruct Dike Access Road, Pipe repair, Repair Concrete Surface, Concrete Coating, Beaver Fencing, Inlet Structure Repairs
Millard Pond Dam – Norwalk, CT – Private Scope: Breach Dam, Remove 12ft Waterwheel, new concrete spillway, bank stabilization
Van Deusen Dam – Roxbury, CT – Private Scope: New granite spillway, upstream corewall, masonry repairs, new masonry viewing area, Pedestrian bridges, 2000lf walking trails
Outdoor World Dam – E Sturbridge, Mass – Private Scope: New Inlet structure, trash Rack, Stop Log structure, piping, earthen Dam
Woodruff Dam – New Preston, CT – Private Scope: New Upstream Concrete Wall, New Cantilevered Spillway, New Inlet piping
Amston Lake Dam – Amston, CT – Lake Association Scope: Crack repair, new Inlet Structure, Stop log structure, Sluice Gate, DI piping, pressure grouting of spillway, cofferdam, cutoff wall
Spring Lake Dam – Southington, CT – Private Scope: Rip Rap slope protection, repair deteriorated spillway, crack and joint repair
Windsorville Dam – Windsorville, CT – Private Scope: Emergency repairs to dam, new concrete wingwall/spillway, cofferdam
Tyler Lake Spillway – Goshen, CT – Town Owned Scope: Emergency repairs to inlet structure gate
Somersville Dam – Somersville, CT – CT DEP Scope: New reinforced corewall, rip rap slope protection, new retaining wall, piping catch basins, concrete crack and joint repair
Waterbury Inlet Structure – Waterbury, CT – CT DEP Scope: Emergency repairs to Inlet Structure, reinforced concrete
Middle River Site 1,2,3,6 – Stafford Springs, CT – CT DEP Scope: New Dikes, Access Roads, New Slopes with Rip Rap Slope Protection, Structure Repair, Crack and Joint Repair, Beaver Fences
Crescent Lake Dam – Enfield, CT – CT DEP Scope: New stepped spillway, New Inlet structure with Sluice Gate, piping, new outlet structure, Rip Rap Slope Protection
Gaylord Pond Dam – Colebrook, CT – Lake Association Scope: New Cantilevered Spillway, Slope Protection, Streambank Protection, raise dike
McLean Game Refuge – Granby, CT – Private Scope: New Fish Passageway, New Diversion Dam, Retaining Walls, streambank protection, Rip Rap Armoring, Remove and Replace Main Dam, Stepped Spillway, cofferdam
Fisher Pond Dam Salisbury, CT – Private Scope: Remove and Replace Dam, 1000 ft rip rap slope protection, cofferdam, DI inlet piping/manhole, cantilevered spillway, cofferdam, raise dike
Towantic Pond Dam- Oxford CT -Private Scope: New concrete cutoff wall installed upstream, New stepped spillway downstream, Installed new outlet structure, Fabricated Fences and gates.
Bromley Pond Dam- Warren CT – Private Scope: Reconstruction of dam and spillway, installed access road.
Lake Beseck Dam- Middlefield CT- State CT DEEP Scope: New concrete cutoff wall installed upstream of existing stone masonry dam, Installed a new low level outlet and stop log structure. Removed existing outlet structure.
Nash Pond Dam- Cornwall CT- Private Scope: Installation of stop log structure and sluice gate
West River Pond Dam- Bethany CT- Private Scope: New concrete cutoff wall installed upstream of existing stone masonry dam, Installed new stop log structure, two sluice gates and trash racks Whole dam face repointed, splash pad and diversion wall for edge of splash pad
Oak Ledge Pond Dam- Sharon CT- Private Scope: Minor Repairs to outlet structure
Hart Pond Dam – Southington CT – Private- Lake Association Scope: Installed low level outlet and rip rap for erosion control
Whitney Dam, Stafford CT -CT DEP Scope: Slope improvements, beaver fence installation and concrete repair
Ellis Dam, Stafford CT- CT DEP Scope: Access improvements, concrete repairs, beaver fence installation, toe drain installation and rip-rap upgrades
Pomeroy Dam, Stafford Ct- CT DEP Scope: Access improvements, beaver fence install, concrete repair, trash rack and minor metal repairs/fabrication and additional rip-rap protection
Shenipsit Dam, Stafford CT- CT DEP Scope: Access improvements, concrete repairs, trash rack metal repairs
Bradway Dam, Stafford CT- CT DEP Scope: Sinkhole repairs, Access Improvements, Concrete Repairs and Trash rack installation
Ellithorpe Dam, Stafford CT- CT DEP Scope: Access improvements, concrete repair, embankment repair, rip-rap added, new trash rack installation
Ashland Pond Dam, Griswold CT- CT DEEP Scope: Embankment repairs, rip-rap added, concrete repairs and sedimentation removal
Glasgo Pond Dam, Griswold CT- CT DEEP Scope, Rip-rap improvements, masonry repair and sedimentation removal
Pachaug Pond Dam, Griswold CT, CT DEEP Scope: Embankment repairs, access upgrades
|